James W. Turner Construction, Ltd.
Internal Project Accounting
Project   25CN0004732
Client   SWFWMD
Report Date   June 11, 2026 (rev. from Jun 10)
Project Profit & Loss Statement

Flint Creek & Peace Creek Debris Removal

Final close-out following agreement expiration · March 31, 2026
Basis of Presentation. Revenue is taken from the QuickBooks invoice register provided by L. Baumgardner on June 10, 2026. Costs are taken from the QuickBooks job-costing report (SWFWD_QB_files_as_of_061026) supplied by G. Miller / C. Zak-Knepper on June 10, 2026. All fifteen invoices submitted to SWFWMD have been collected in full (final payments cleared June 9, 2026). Allocated corporate overhead, project management labor (Patrick Haygood), insurance, bonding, and corporate G&A are excluded; see Note 4.

Executive Summary

Revenue Earned
$1,089,688
15 invoices, 100% collected
Job-Costed Direct Costs
$864,873
Per QuickBooks job-cost report¹
Gross Profit, Pre-Overhead
$224,815
20.6% gross margin
Contract Value (Am. 2)
$1,505,065
$1,803,850 original less Am. 2 reduction
Percent Earned
72.4%
$415,377 ceiling unutilized
Cash Receipts
$1,089,688
All collected by 6/9/26

The project earned $1,089,688 in revenue against $864,873 in direct costs per the QuickBooks job-cost report, producing a gross profit of $224,815 (20.6% margin) before any allocation of corporate overhead, project management time, or insurance/bonding. Flint Creek closed at 100% of contracted scope. Peace Creek substantially completed against amended scope with the final demobilization invoices submitted in April 2026.

Contract Position

DocumentDateDescriptionAmount
Master AgreementJun 13, 2025Original Schedule of Values$1,803,850.49
Amendment 1Jul 24, 2025Administrative — no financial change
Change Order No. 1Oct 31, 2025Piling removal at Hwy 301 (drawn from Flint contingency)20,000.00
Amendment 2Dec 18, 2025Removed Peace Creek Panels 14–16 (50,216 LF); extended deadlines(298,785.20)
Amended Contract Ceiling$1,505,065.29

Schedule of Revenue

Invoice Date Description Amount Payment Ref Status
Flint Creek — $203,357.61
FlintCreek110/07/25Flint Mobilization 50% + P2 (772 LF)$29,593.40906696018268353
FlintCreek210/07/25Flint P1 + P2 (5,603.6 LF)33,341.42906696018268353
FlintCre3.111/07/25Mobilization additional 25%12,500.0026EF0000620
FlintCre3.211/07/25P1 + P2 remainder + P3 full (8,359.8 LF)49,740.8126EF0000609
FlintCreek412/29/25P2 final + Erosion Control16,982.5626EF0001562
FlintCreek512/29/25Mobilization final 25%12,500.0026EF0001562
FlintCrkCO112/29/25CO #1 — Piling Removal at Hwy 30120,000.0026EF0001562
FlintCrHaul04/06/26Hauling / Tipping (62.49 tons)3,699.4226EF0001983
Demobilization04/09/26100% Demobilization25,000.0026EF0001983
Peace Creek — $886,330.86
PeaceCreek110/07/25Mobilization 25% + P2 debris (10,771.2 LF)$70,338.64906696018268353
PeaceCreek212/17/25Mobilization 25% + multi-panel debris327,905.8126EF0001563
PceCrk2Rev02/26/26Invoice 2 supplemental (SWFWMD revision)67,877.6026EF0001563
PeaceCreek303/23/26Panels 4, 9-Upper, 10, 12 debris257,664.7526EF0001721
PeaceCrFinal04/06/26Panels 7, 13 + Mob residual + Erosion Control158,977.1526EF0001722
PeaceCrHaul04/06/26Hauling / Tipping (67.64 tons)3,566.9126EF0001984
Total Revenue Earned & Collected$1,089,688.47

Schedule of Direct Costs — per QuickBooks Job-Cost Report

Cost Category Class Amount % of Costs
Subcontractor (Insured) — HD WorxsUnclassified¹$554,155.6564.2%
Subcontractor (Insured) — FLUnclassified¹182,996.1321.2%
Total Subcontractor Costs$737,151.7885.4%
Equipment Rental — Marsh Master + MiscUnclassified¹68,875.008.0%
Equipment Rental — CAT 309 AmphibiousPeace Creek37,300.004.3%
Equipment Rental — Mini Excavators (Apr 2026)Flint Creek11,127.421.3%
Total Equipment Rental$117,302.4213.6%
Miscellaneous Construction CostsUnclassified¹8,422.791.0%
Reimbursable Expenses (12/16/25 NC STEP allocation)Flint & Peace Creek1,996.190.2%
Total Direct Project Costs (Job-Costed)$864,873.18100.0%

Statement of Operations

Contract Revenue Earned$1,089,688.47
Less: Subcontractor Costs (HD Worxs + FL)(737,151.78)
Less: Equipment Rental(117,302.42)
Less: Miscellaneous Construction(8,422.79)
Less: Reimbursable Expenses (12/16/25)(1,996.19)
Total Direct Costs (Job-Costed)(864,873.18)
Gross Profit, Pre-Overhead$224,815.29
Gross margin percentage20.6%
Note: This statement is presented pre-overhead. A standard JWTC corporate allocation (G&A, PM labor, insurance, bonding) is estimated to reduce profit by an additional $75,000 – $135,000.

Open Items — Resolved by Glen Miller (June 11, 2026)

All three open items confirmed; figures updated above

  1. HD Worxs cash advances — already in costs. Confirmed: The $448,000 in HD Worxs advances is already included within the $864,873 total direct costs. The monthly General Journal accruals to the "Sub Insured — HD Worxs" account represent the cost recognition; the advances themselves were funding entries, not separate cost line items. No change to total cost.
  2. $200,000 cash advance dated 12/05 — Sarasota project. Confirmed: The 12/05/2024 wire is a Sarasota project advance, not Flint & Peace. Correctly excluded from this statement. No change to total cost.
  3. Brian Benoit reimbursement dated 12/16/25 — partially allocable to F&P. Confirmed: $1,996.19 of the 12/16/25 reimbursement (NC STEP check) is allocable to Flint & Peace Creek. Added to direct costs above as a new line item under "Reimbursable Expenses (12/16/25 NC STEP allocation)." Gross profit reduced by $1,996.19 from prior $226,811.48 to $224,815.29.

Quantity & Scope Completion

Project Contract LF (Am. 2) LF Completed % Complete Status
Flint Creek 15,909 15,909 100.0% Closed out
Peace Creek (per panels billed) 173,018 ~129,500 ~74.9% Substantial completion
Combined 188,927 ~145,400 ~77.0% 72.4% by contract value

Notes to the Statement

1. "Unclassified" cost class. The majority of project costs ($814,450 of $862,877) are booked to the "Flint & Peace Creek 2025 — Other" account because the original posting did not assign a Flint or Peace Creek class code. Glen Miller is in the process of reclassifying these entries by sub-project; the total project cost is not expected to change materially, but the Flint-vs-Peace split will be adjusted.

2. Revenue recognition. Revenue is recognized when invoiced to SWFWMD. All fifteen invoices have been collected per the QuickBooks payment register (final payments cleared June 9, 2026). PceCrk2Rev represents a supplemental invoice issued in response to SWFWMD's January 2026 revision request — the original PeaceCreek2 invoice was paid as billed and the revision added $67,877.60 of additional revenue rather than reducing the original.

2a. Update — June 11, 2026. All three open items previously pending Glen Miller's confirmation have been resolved. HD Worxs advances ($448K) are confirmed to be already embedded in the cost total (no change). The 12/05/2024 $200K advance is confirmed Sarasota (no change). The 12/16/2025 Brian Benoit reimbursement (NC STEP check) is allocable to F&P at $1,996.19 and has been added; gross profit revised from $226,811.48 to $224,815.29 (margin 20.8% → 20.6%).

3. Subcontractor reconciliation. HD Worxs (Indy A-Team Services, LLC) was the primary subcontractor. Total subcontractor costs of $737,152 reflect both HD Worxs's direct invoiced amounts and pass-through costs that JWTC paid on behalf of HD Worxs (lodging on BOA card, equipment share rentals, Marsh Master rentals, boat storage). A final accounting and lien waiver from HD Worxs is being requested for project close-out.

4. Excluded costs. This statement does not include allocated corporate G&A, project management labor (Patrick Haygood), insurance, bonding, or banking fees. A standard JWTC overhead allocation is estimated at $75,000 – $135,000. Also excluded are the time investments of Charlene Zak-Knepper, J.W. Turner, and Brian Benoit during the multi-month subcontractor reconciliation process — these may be allocated separately as part of a portfolio-level cost analysis covering Sarasota, Flint & Peace Creek, and Baltimore.

5. Source documents. SWFWMD Agreement 25CN0004732 and amendments; all 15 invoice PDFs; the QuickBooks register dated June 10, 2026 (Flint_Peace_Qbooks, SWFWD_QB_files_as_of_061026); HD Worxs Nov 30 itemization and W10/W11 detailed cost reports; Cheri Vallery's cash register through November 2025; Patrick Haygood's Dec–Feb crew reimbursement (REVISED); individual crew payment receipts; BOA lodging schedules; EquipmentShare and Marsh Master rental records; Sarasota / FDEM portfolio reconciliation files dated 02.01.25 and 06.10.26.

Close-Out Items

  1. Resolve three open items with Glen Miller (above). Email sent to Glen on 6/10/26 with three specific questions. Item 1 (advance classification) is the highest-impact — if advances are separate from cost accruals, gross profit could fall to as low as $0.
  2. Reclassify "Unclassified" QuickBooks entries to Flint or Peace. $814,450 of cost is currently in the catch-all "Other" bucket. Glen to re-class so the Flint Creek vs Peace Creek split is accurate. Total cost figure will not change.
  3. HD Worxs final accounting and lien waivers. Obtain written final settlement from Travis Aubert / David Frederick. Required for audit-readiness and contract close-out documentation.
  4. Apply JWTC corporate overhead allocation. Agree allocation method (corporate G&A, Patrick PM time, insurance, bonding) and book a closing journal entry to bring the statement to fully-burdened P&L.
  5. Portfolio-level reconciliation (Sarasota / F&P / Baltimore). Per C. Zak-Knepper's request, a separate three-project portfolio summary will follow, including equipment carrying costs (interest, property tax, insurance) and time allocation for Charlene, JW, and Brian during the four-month reconciliation process.
Prepared by Internal Project Accounting For internal management use only · Not a financial audit
James W. Turner Construction, Ltd.
25CN0004732 · Updated Jun 11, 2026